How to Size a Diesel Generator for Your Equipment

Engineer reviewing drawings and a load schedule beside generator equipment

Generator sizing begins with the equipment you need to power and how it operates. Adding equipment nameplate figures gives a useful starting point, but it does not show every starting demand or the largest load change the generator will experience.

Build a running-load schedule

List each item, quantity, electrical input power, voltage, phase and frequency. Identify which items operate together. For motors, check whether the stated kW is mechanical shaft output or electrical input; the two should not be treated as identical.

Use measured operating demand or equipment data where available. Keep uncertain values marked as estimates, so the supplier can see which assumptions still need checking.

Check kW, kVA and power factor

kW describes real electrical power, while kVA describes apparent power. For the same operating condition, kW = kVA × actual power factor. Power factor belongs to the load and is not universally 0.8. Both the generator’s real-power capacity and the alternator’s current capacity must be adequate.

As an illustration, assume a balanced three-phase load draws 60 kW at a measured total power factor of 0.9. Its running apparent demand is approximately 60 ÷ 0.9 = 66.7 kVA. This calculation describes only that assumed running condition; it does not select a generator.

Welder working on a steel fabrication in an ordinary workshop

Assess starting and load steps

Request motor starting data and the starting method, such as direct starting, a soft starter or a variable-speed drive. Use equipment-specific information instead of a universal starting-current multiplier.

In the example above, a pump starting while other equipment runs may set the critical load step. The supplier should check the resulting voltage and frequency changes against the equipment’s acceptable limits. An agreed starting sequence can change the demand the generator must accept at once.

Apply duty and site conditions

Confirm whether the project needs standby, prime or another duty rating. Provide altitude, expected ambient temperature and installation information. Capacity adjustments must follow the offered engine and alternator data, rather than a general percentage per metre or degree.

Separate planned expansion from an arbitrary sizing margin. Ask for a proposal showing the load assumptions, transient assessment and available site-rated output. Browse NPC power ranges, then send NPC your load schedule for a project-specific enquiry.